top of page
Garage Point

Garage Point

Morrison, CO

Tilt-Up Efficiency Amid Challenging Conditions

Symmetry executed the Garage Point project — a six-building tilt-up complex with 165 tilt-up panels and 112,000 SF of concrete slab in a challenging hillside environment. The site’s topography required specialized sequencing and rigging to safely install the panels adjacent to the slope. Through careful planning and execution, Symmetry delivered a durable and functionally efficient industrial complex under complex conditions.

Completed Date

2024

Delivery Method

​

Building Size

112,000 SF

Owner

Project Duration

18.0 Months